First week over at Versa Studios Leeds
- cdmechanical
- Oct 18, 2020
- 1 min read
Stainless press Gas system installed in the first unit with some water feeds at various points. First fix is now done now awaiting delivery of the Reznor heaters due next week. All pipework tested and ready for 2nd fix. 💪.